Blocks for 10 ft of wall
| Height above ground | 12 × 4 in block, 7 in deep | 16 × 6 in block, 10 in deep | 18 × 8 in block, 12 in deep |
|---|---|---|---|
| 1 ft | 50 blocks, 0.61 yd³ stone | 24 blocks, 0.43 yd³ stone | 21 blocks, 0.56 yd³ stone |
| 2 ft | 80 blocks, 1.14 yd³ stone | 40 blocks, 0.86 yd³ stone | 28 blocks, 0.8 yd³ stone |
| 3 ft | 110 blocks, 1.66 yd³ stone | 56 blocks, 1.3 yd³ stone | 42 blocks, 1.3 yd³ stone |
| 4 ft | 140 blocks, 2.19 yd³ stone | 72 blocks, 1.73 yd³ stone | 49 blocks, 1.54 yd³ stone |
Worked out by the calculator above, with the buried courses and before any extra or caps. The stone is the drainage stone behind the blocks; the leveling pad adds 0.37 yd³ of base per 10 ft under a 7 in block, ordered loose.
The formula
The pad is ordered loose: Quikrete’s patio guide tamps about 5 in of gravel to 4. The gravel calculator turns any other volume of base or stone into tons, and the paver calculator works out a patio at the foot or top of the wall.
How the wall goes together
Dig a level trench and compact the soil, then the leveling pad, checked level front to back and side to side. Lay the first course on it, buried, starting at the lowest end; on a slope, step the pad up by a block’s height rather than slope the blocks. Fill the blocks’ cores and the gaps between them with ¾ in clean stone, lay the drainpipe behind the first course, and backfill each course with stone directly behind the blocks and compacted soil behind that, 6 in at a time. Pull each block forward to its setback, stagger the joints, and glue the caps on with concrete adhesive. Finish with soil that slopes water away from the top of the wall; the mulch and topsoil calculator works out the topsoil and mulch for a bed behind it. A mortared wall of concrete block is a different build, on a concrete footing: the concrete block calculator counts its blocks and mortar.
Questions people ask
How many retaining wall blocks do I need?
Blocks per course is the wall’s length over the block’s, rounded up; courses are the height over the block’s height, plus the buried ones. A 10 ft wall 2 ft high of 12 × 4 in blocks takes 10 a course and 8 courses, 2 of them below ground: 80 blocks before the extra.
How deep do you bury the first row of a retaining wall?
Belgard buries the first course at least 6 in, on a leveling pad of ¾ in minus base at least 6 in deep after compaction that runs 6 in past the front and back of the block. So the trench goes 6 in below the bottom of the block and is 12 in wider than it. A taller wall’s plans may bury it deeper.
How much gravel goes behind a retaining wall?
Belgard fills at least 12 in behind the back of the block, or 24 in from its face if that is more, with ¾ in clean stone, up to 6 in below the top, where low-permeability soil caps it. A perforated drainpipe runs at the bottom, with an outlet at least every 50 ft. For 10 ft of 2 ft wall in 12 × 4 in blocks, that is 1.14 yd³ of stone.
How tall can a retaining wall be without an engineer?
Belgard recommends a professional engineer design any wall over 4 ft high. Below that, a wall with a load above it (a slope, a drive, a fence or a building), on poor soil, or in tiers can still need geogrid and a design, and some small blocks are rated for walls of only 2 ft. Check the maker’s chart for your block, and your local code.
Sources for the numbers on this page
- Belgard: Technical Resource Guide: retaining wall installation (6 in leveling pad, 6 in burial, 12 in of drainage aggregate, engineer over 4 ft) · checked
- Vulcan Materials: Construction aggregates calculator: estimated density by rock and product (lb/ft³) · checked
- Quikrete: Building a concrete patio — project guide (2×4 forms, stakes at 3 ft, 4 in compacted gravel, ½ in isolation joint) · checked
Corrections and updates are logged on the sources page.