What each group counts
- Concrete comes from the slab calculator: the slab’s volume with 10% extra, as cubic yards to order from a ready-mix plant, and as 80 lb bags at the maker’s yield if you mix by hand. Above about a cubic yard it suggests a ready-mix quote.
- Rebar comes from the rebar calculator: bars each way at 12 in on center, 3 in clear of the edges, in 20 ft lengths, lapped 40 bar diameters where a run is longer than a bar. A round slab gets no grid here; lay its bars out by hand.
- Forms follow Quikrete’s patio guide: 2× boards around the perimeter in stock lengths, as deep as the slab is thick, a stake every 3 ft and two 3 in screws per stake. A round slab gets a flexible form the length of its circumference.
- Base is the same guide’s 5 in of compactible gravel, tamped to 4 in, over the slab’s area.
- Joints: the ½ in asphalt-impregnated isolation strip along any edge you say meets a structure, and how many control joints to cut so no panel is more than 8 ft across.
- Curing: acrylic cure & seal at 200 sq ft a gallon, or keep the slab wet under plastic sheeting instead. The evaporation calculator says how fast today’s weather will dry it.
How to use it
- Measure the finished slab: the outside of the forms, and the thickness you’ll pour. 4 in is usual for a patio or walk; a driveway is 5 to 6 in.
- Say which edge meets the house, a foundation or another slab, so the list adds the isolation strip for it.
- Adjust what the slab doesn’t say. Bar size and spacing, bag size, the extra to order and the prices live on the calculators; each group’s “Adjust” link opens its calculator with the slab filled in, and this browser keeps the slab.
- Copy the list and paste it into a quote request, or print it as the order sheet.
Before you pour
Your permit office decides what applies where you live: slab thickness, reinforcement, frost protection and whether a vapor barrier is needed. The slab calculator explains the IRC minimums it checks, and the slab thickness guide covers the common jobs.
What you still need to count
Chairs or bricks to hold the rebar at mid-depth and tie wire for the crossings; form release; a vapor barrier under a slab that becomes a floor; a bull float, edger and jointer or the saw to cut the joints; plastic sheeting if you cure under it; and the permit fee. Mesh, fiber-reinforced mix and ready-mix delivery and short-load fees are priced by your supplier.
Questions people ask
What do I need to pour a 10 × 10 patio?
At 4 in thick: 1.36 yd³ of ready-mix (33.3 ft³ plus 10% extra), or 62 bags of 80 lb concrete mix if you mix it yourself; ten 20 ft #4 bars for a grid 12 in on center; four 10 ft 2×6 form boards, 14 stakes and 36 screws; 1.5 yd³ of gravel for a 4 in compacted base; and a gallon of acrylic cure & seal. Add the length of the edge against the house and the list adds the ½ in isolation strip. Two control joints keep every panel under 8 ft.
Are the quantities the same as on the slab and rebar calculators?
Yes. The concrete is the slab calculator’s figure for this slab with its 10% extra, and the bars are the rebar calculator’s grid at its defaults: #4 bars 12 in on center, 3 in clear of the edges, in 20 ft lengths lapped 40 diameters. “Adjust” beside either group opens that calculator with the slab filled in; what you change there comes back to the list on this browser.
Where do the forms, base and curing figures come from?
From Quikrete’s published project guides. The patio guide builds the forms from 2×4s staked every 3 ft, spreads about 5 in of compactible gravel and tamps it to 4 in, and glues a ½ in asphalt-impregnated fiber board where the slab meets a structure. The sidewalk guide cuts control joints every 6 to 8 ft in a 4 in slab, a quarter of the thickness deep. The cure & seal data sheet gives 200 sq ft a gallon. The list applies those rules to your slab’s perimeter and area; the form boards come in the stock lengths lumber yards carry.
Why 2×6 form boards for a 4 in slab?
A 2×4 is 3½ in deep, so Quikrete’s guide pours 3½ in of concrete in 2×4 forms. For a 4 in slab the list picks the first board as deep as the slab is thick, a 2×6 at 5½ in. Many people set 2×4 forms half an inch proud of the base instead; if you do, buy 2×4s in the same lengths.
What isn’t on the list?
Anything the guides don’t quantify: rebar chairs and tie wire, form release (the guide uses vegetable oil), a vapor barrier where a slab becomes a floor, mesh if you use it instead of bars, tools, and the permit. The how-much-concrete guide walks the whole job.
Sources for the numbers on this page
- Quikrete — Concrete Mix No. 1101 — technical data sheet (bag yields, strength gain, curing) · checked October 1, 2026
- Sakrete — Estimating bagged concrete jobs · checked October 1, 2026
- State of Ohio (adopted IRC text) — Residential Code of Ohio 4101:8-5-01 — R506.1 concrete floors on ground (3½ in minimum) · checked October 1, 2026
- Caltrans — Bridge Design Details, ch. 13 — ASTM A615 bar sizes, areas and weights · checked October 1, 2026
- Element ICF — TB-4 Lap splices (IRC Table R608.5.4(1) values for Grade 40 and Grade 60) · checked October 1, 2026
- Quikrete — Building a concrete patio — project guide (2×4 forms, stakes at 3 ft, 4 in compacted gravel, ½ in isolation joint) · checked October 11, 2026
- Quikrete — Concrete sidewalks and small slabs — project guide (control joints every 6 to 8 ft, ¼ of the thickness deep) · checked October 11, 2026
- Quikrete — Acrylic Concrete Cure & Seal No. 8730 — data sheet (200 sq ft per gallon) · checked October 11, 2026
- National Ready Mixed Concrete Association — CIP 11 — Curing in-place concrete · checked October 1, 2026
- Southern Forest Products Association — Southern Pine standard sizes (nominal and actual dimensions) · checked October 3, 2026
- Southern Forest Products Association — Southern Pine specification guidelines (standard lengths, 8 to 20 ft in two-foot steps) · checked October 4, 2026
Corrections and updates are logged on the sources page.