What each group counts
- Pavers and edging: the pavers come from the paver calculator, each with its share of the ⅛ in joints and 5% extra for cuts and breakage, rounded up to whole pavers. The edge restraint runs around the patio’s four sides, set on the base, which is why the base runs past every edge.
- Base and sand come from the same calculator: crusher run to Belgard’s minimum depth for the use (4 in for a patio or walk, 6 in for a driveway, 8 in for a parking area), 6 in wider than the patio on every side and ordered a quarter deeper loose than compacted, and 1 in of concrete sand under the pavers, in cubic yards and in tons at Vulcan Materials’ densities.
How to use it
- Measure the patio as it will be finished, edge to edge. For an L or a curve, split it into rectangles and run the list for each, or use the paver calculator’s area.
- Choose the paver by the size on its label. Some makers give a size that already includes the joint: the paver calculator takes that with a 0 in joint.
- Price it with your supplier’s prices, or copy the list into a quote request. Quarries sell base by the ton: the note under each line gives the tons.
Before you dig
Have buried lines marked before digging, and slope the base at least 2% away from the house so water runs off.
Questions people ask
What do I need for a 12 × 10 ft paver patio?
With 4 × 8 in pavers and ⅛ in joints: 542 pavers (516 plus 5% for cuts), 44 ft of edge restraint, 2.21 yd³ of crusher run (4.11 tons) for a 4 in base that runs 6 in past every edge, and 0.37 yd³ of concrete sand (0.55 tons) for the 1 in bed. Dig 7⅜ in below the finished surface; Belgard says at least 8 in, more where the ground freezes.
Are the quantities the same as on the paver calculator?
Yes: every line but the edging is the paver calculator’s result for this patio, with its defaults for what the list doesn’t ask (⅛ in joints, 5% extra). “Adjust” opens the paver calculator with the patio filled in, and a change there to the patio comes back to the list on this browser. The gravel calculator starts from the patio’s length and width too, for a base of another stone or depth.
How do I price the list?
Press “Add your prices” and type your yard’s or store’s price beside each line: per paver, per foot of edging, per cubic yard of base and sand. The list adds them up, and the copied text and the CSV carry them. The site gives no prices of its own: they change by week and by store, and every figure here has a source. Your prices stay on this device with the patio until you press “Start over”.
What isn’t on the list?
The joint sand, whose coverage depends on the product and the joint width (its bag says), the spikes for the edging, a geotextile where the soil is soft, and the rental of a plate compactor and a saw for the cuts. A retaining wall or steps around the patio are their own job: the retaining wall calculator counts a wall’s blocks, caps and stone.
Does the list remember my patio?
On this device, yes: the patio is kept in your browser’s local storage, so the paver and gravel calculators and this page start from it until you press “Start over”. The link in the address carries the same patio, so it can be sent or bookmarked. Nothing is stored on the site.
Sources for the numbers on this page
- Belgard: Technical Resource Guide: paving systems installation (base 4 in for patios, 6 in for driveways; 1 in bedding sand; ⅛ in joints) · checked
- Vulcan Materials: Construction aggregates calculator: estimated density by rock and product (lb/ft³) · checked
- Quikrete: Building a concrete patio — project guide (2×4 forms, stakes at 3 ft, 4 in compacted gravel, ½ in isolation joint) · checked
Corrections and updates are logged on the sources page.